Civil Engineering MCQ’s
1. The process of taking out stones from
natural rock is known as
(a) Weathering
(b) Quarrying
(c) Dressing
(d) Cladding
2. What is the full form of PVCN with respect to
Paint?
(a) Pigment Volume Concentration Number
(b) Paint Volume Concentration Number
(c) Paint Volume Carbon Number
(d) Pigment Volume Carbon Number
3. The diameter of the sieve used for finding
liquid limit is _____.
(a) 425 microns
(b) 375 microns
(c) 125 microns
(d) 250 microns
Ans. (a)
4. Basic value of span to effective depth ratio
for span up to 10 m for cantilever is _____.
(a) 20
(b) 7
(c) 12
(d) 5
5. The minimum furrow grade to assure
surface drainage is _____.
(a) 0.09%
(b) 0.02%
(c) 0.07%
(d) 0.05%
6. The dimensions for the special shape of clay
bricks are given in
(a) IS : 3461 – 1966
(b) IS : 1464 – 1969
(c) IS : 6165 – 1971
(d) IS : 3951 – 1975
7. The longitudinal of friction on highway for
calculation of stopping distance in geometrical
design is _____.
(a) 0.35 to 0.4
(b) 0.25 to 0.29
(c) 0.5
(d) 0.3 to 0.34
8. The minimum cover for an RCC column
should be
(a) Greater of 40 mm or diameter
(b) Greater of 30 mm or diameter
(c) Greater of 50 mm or diameter
(d) Greater of 25 mm or diameter
9. Which of the following dams is classified
based on structural design?
(a) Gravity dam
(b) Diversion dam
(c) Storage dam
(d) Detention dam
10. Which vibrator is used for vibrating
concrete cubes?
(a) Surface vibrator
(b) Internal vibrator
(c) Platform vibrator
(d) Table vibrator
11. For most economical section using Chezy’s
formula, depth of flow for maximum discharge
through circular channel of diameter d is ____.
(a) 0.5 D
(b) D
(c) 0.95 D
(d) 0.3 D
12. The coefficient of discharge for
venturimeter ( ) ranges from _____.
(a) 0.50 – 0.55
(b) 0.61 – 0.65
(c) 0.61 – 0.69
(d) 0.95 – 0.99
13. The process of maintaining the moisture
and temperature conditions of concrete so that
concrete develops hardened properties over
time is called _____.
(a) Softening
(b) Curing
(c) Hardening
(d) Setting
14. If B = 100 days and D = 1400
hectares/cumec, then find delta
(a) 65.71 cm
(b) 61.71 cm
(c) 55.71cm
(d) 51.71 cm
15. An error due to the earth’s curvature and
refraction is to be corrected using
(a) = 0.0136 D²
(b) = 0.0673 D²
(c) = 0.0785 D²
(d) = 0.0112 D²
16. The disposal of the screen is done by
(a) Sedimentation
(b) Flocculation
(c) Filtration
(d) Incineration
17. The scrap value of a building may be about
____ percentage of the total cost of construction.
(a) 5%
(b) 1%
(c) 10%
(d) 7%
18. Temporary spurs are also called _____.
(a) Weirs
(b) Canals
(c) Bunds
(d) Barrages
19. Common glass is known as _____.
(a) Potash lead glass
(b) Soda-lime glass
(c) Bottle glass
(d) Borosilicate glass
20. A procedure of actual costing and valuing
an item of work on the basis of labourers and
materials required is _____.
(a) Day work
(b) Provisional sum
(c) Lump sum amount
(d) Prime cost